Choose between lift and shift, lift-shift-migrate, and lift-shift-migrate to HANA

A worked example

Yes or no

Fabrikam runs a production SAP ERP system on an Oracle database in its own datacenter. The system must be moved to Azure virtual machines, upgraded to a new SAP release, and migrated to SAP HANA. The business sets two requirements:

  1. The production system may have only one downtime for the whole project.
  2. The approach must be one that SAP officially supports for migrations to the cloud.

The team is comparing three approaches:

  • Approach 1: Lift and shift the system to Azure, then run DMO in Azure.
  • Approach 2: Classical DMO run from the on-premises application server directly against SAP HANA in Azure.
  • Approach 3: DMO with system move ("Enable the migration with system move" in SUM).

For each of the following statements, select Yes if the statement is true. Otherwise, select No.

StatementYesNo
Approach 1 meets the downtime requirement.

A lift and shift followed by DMO requires two downtimes and two testing cycles, but Fabrikam allows only one downtime.

Correct
Approach 2 meets the support requirement.

For classical DMO, a cloud migration is technically possible but is not currently officially supported by SAP, so it fails the second requirement.

Correct
Approach 3 meets both requirements.

DMO with system move is intended for cloud/Azure-based migrations: SUM starts on the on-premises application server, stops at the execution phase, and continues the import on a new application server in Azure. As a DMO process, it performs the upgrade and the SAP HANA migration in one step.

Correct
Why

The two-step approach (lift and shift, then DMO) needs two downtimes, so it fails the single-downtime requirement. Classical DMO can technically reach the cloud, but SAP does not currently officially support it for that use, so it fails the support requirement. DMO with system move is the DMO variant designed for Azure migrations: SUM runs on the on-premises source, and after the SUM directory is copied the import continues on new servers in Azure. This combines the upgrade and HANA migration in one step and meets both requirements.