A team is preparing a migration workstream for implementation. Its draft contains prerequisites, ordered implementation tasks, rollback commands, checks required before advancing, and verification after migration. During a rehearsal, engineers can execute the rollback but cannot agree which observed conditions require them to stop the migration and revert.
What should you add to the workstream plan to resolve this gap?
Rollback commands explain how to revert, but the team also needs rules for deciding when to revert. Measurable criteria for each phase make those stop-and-rollback decisions explicit within the implementation flow.
- Correct: Specific, measurable conditions that trigger a rollback decision in each implementation phase. The source requires explicit, measurable rollback criteria for each phase. These provide the decision rules missing from the otherwise executable plan.
- Not correct: More detailed rollback commands, execution instructions, and command examples for each implementation phase. The execution procedure is already usable. The source explicitly distinguishes rollback steps from the criteria that determine when to use them.
- Not correct: Additional post-migration verification checks and validation of the final state after the migration. The source includes post-migration verification as a separate part of the implementation plan. Adding final checks does not define conditions for stopping and reverting during execution.
- Not correct: Named implementation owners, responsibility assignments, and estimated completion dates for each migration phase. The source includes responsible teams and duration estimates when organizing workstreams. Those additions allocate work but do not supply the rollback decision conditions missing here.