Two standalone Windows Server Hyper-V hosts replicate a VM. HV-P currently runs the primary VM, and HV-R holds its replica. Both hosts are configured to receive replication.
Administrators will move production to HV-R during scheduled maintenance on HV-P. Both hosts will be reachable for each switchover. The procedure must transfer outstanding changes before each production switchover. The application will create new data while running on HV-R; those changes must be replicated back to HV-P before production returns there.
Which supported sequence should the maintenance runbook specify?
Use planned failover for each scheduled switchover so that remaining changes reach the destination before it takes over. After the outbound move, HV-R is the primary and must replicate its new changes toward HV-P. The return planned failover therefore starts from HV-R.
- Not correct: Unplanned failover from HV-R; reverse replication HV-R → HV-P; planned failover from HV-R. The source warns that an unplanned failover can lose changes. It does not provide the final transfer of outstanding changes described for a planned failover.
- Not correct: Planned failover from HV-R; reverse replication HV-R → HV-P; planned failover from HV-R. The first planned failover must be initiated from HV-P, which initially hosts the primary VM. The source places initiation of a planned failover on the primary host.
- Not correct: Planned failover from HV-P; reverse replication HV-P → HV-R; planned failover from HV-R. After the first failover, HV-R contains the new production changes. The source describes reversing replication toward the original primary, so the required direction is HV-R → HV-P.
- Correct: Planned failover from HV-P; reverse replication HV-R → HV-P; planned failover from HV-R. The first planned failover transfers remaining changes and makes HV-R primary. Reverse replication then updates HV-P, and the return planned failover starts from HV-R because it is the current primary.
- Hyper-V Replica overviewMicrosoft Learn