You are creating a production Lakeflow Job from four workspace notebooks: ingest_data, transform_customers, transform_orders and train_model. The job must meet these requirements:
- The transform tasks must not start until
ingest_datacompletes successfully. - The dependencies must allow the two transform tasks to run in parallel to minimise total job duration.
train_modelmust not start until both transform tasks complete successfully.
Which job configuration meets all the requirements?
Choose one answer.
- Source Workspace for all tasks; transforms chained after
ingest_datain sequence;train_modeldepends ontransform_orders. - Source Workspace for all tasks; both transforms depend on
ingest_data;train_modeldepends on both transforms. - Source Workspace for all tasks; both transforms depend on
ingest_data;train_modeldepends ontransform_orders. - Source Workspace for all tasks; both transforms have no dependencies;
train_modeldepends on both transforms.